FlamesNation has no direct affiliation to the Calgary Flames, Calgary Sports and Entertainment, NHL, or NHLPA
Scotia Place: a street-level look at construction progress from late August 2026
alt
Ryan Pike
Aug 25, 2026, 12:00 EDTUpdated: Aug 25, 2026, 03:17 EDT
Pals, there has been a ton of construction activity around Scotia Place since the summer began. If you’ve followed along with our updates over the last while, you’ve probably seen things transform from a somewhat incomplete building skeleton to, well, a structure that looks pretty close in same areas to what it’ll end up being on opening night for the 2027-28 season.
It’s been about a month since our last snapshot of progress, so let’s dive in!

Southwest corner

This week:
Four weeks ago:
We’ll start here: no substantial changes on this side. There’s some work being done on the south side – we’ll get a better look at that elsewhere – but as we’ve noted before, this corner was the first area where work got going and so it makes sense that it’s the furthest along.
Here’s some concept art for the finished product:
courtesy City of Calgary

Northwest corner

This week:
Four weeks ago:
There’s a bit of progress on this view, primarily some work moving along the angular steel facades, but the real progress is on the other sides.
As with the prior stopover, here’s the concept art of the finished product:

Northeast corner

This week:
Four weeks ago:
On the day we were roaming around, there were a ton of concrete mixer truckers on site – we counted eight. That’s a reflection of just how much work is being done on this side of things. Hey look, the building envelope has almost entirely been installed, which has been followed by things progressing on the parkade side – we’ll get to that in a bit.

Southeast corner

This week:
Four weeks ago:
This is the view that showcases the most progress, so let’s run through it. The green building envelope panelling has worked its way almost entirely around the building, with just a couple smaller gaps in the overall coverage – we suspect the sides of the main bowl structure will be fully enclosed fairly soon. In roofing progress, the big white crane is gone and it appears that much of the roof structure has been installed. (We’ll get to that in a moment.)
If we zoom in from Scotsman’s Hill: hey look, a bunch of the exterior glass and glazing has been installed on the south side of the main entrance to the building! And you can also notice from this zoomed-in view that a lot of the exterior envelope and other panelling is being installed on the angular framing around the entrance.
Here’s concept art of how that’ll look when it’s all done:
Now, onto a couple questions that we’ve been tracking over the last little while…

Hey, is the roof done?

Our simple answer is: enough of the roof is done that it’s tough to approximate how much of the roofing is left to finish without a drone, which we do not have (and won’t be getting). Based on the glimpses we have from the current gaps in the exterior envelope panelling, our current viewpoint is the roof is mostly done, albeit with a bit of a gap in the middle that they’re obviously going to fill in before things get chilly later in the fall.
We can see a bit of daylight from the east side of the building, so it’s not completely covered yet. But it’s getting close.

How has the parkade progressed?

Here are a couple snapshots from Scotsman’s Hill of the progress in pouring the parkade over the past month.
This week:
Four weeks ago:
A lot of the concrete structure is being poured. Based on the number of mixer trucks we saw around the site, that should keep progressing – potentially quite quickly – over the next little while.
We’ll check back in again in a few weeks as we get a little closer to the hockey season!

Past construction updates:

Stay tuned for more Scotia Place construction update as things work their way towards completion and opening night!

This article is brought to you by Crystal Waters

Crystal Waters is your Crystal Clear Choice for Home Comfort Solutions, including all plumbing, heating, and cooling equipment repairs, maintenance, and installation. Founded in 2001, and completing over 30,000 projects, our qualified professionals are the guardians of your home’s mechanical heart.
Call Crystal Waters Plumbing and Heating today at 403-219-4100 for a complete mechanical system audit, and learn how we can partner with you to ensure your home is optimized for safety, health, and comfort. Or check them out at www.crystalclearcalgary.com
Daily FaceoffPuckPedia